Blasting Site Coordination and Cooperation - Blasting Vibration Meter
On-site Responsibilities of the Monitoring Unit
(1) Submit the blasting vibration monitoring plan for the owner's approval; submit the layout drawing of monitoring points before each vibration monitoring.
(2) Appoint an on-site liaison to coordinate cooperation between the two parties.
(3) Start preparation for blasting vibration at least 2 hours in advance, complete it 30 minutes ahead of time, and notify the on-site guard supervisor.
(4) Observe on-site blasting safety regulations to ensure the safety of personnel and equipment.
(5) After the blasting vibration meter test is completed, clean up the work site promptly.
(6) Submit the monitoring results of the blasting vibration meter in a timely manner.
Cooperation Work of the Civil Contractor
(1) Designate the on-site work liaison to coordinate the cooperation between the two parties.
(2) Provide the excavation blasting construction plan.
(3) Inform of the blasting schedule at least 1 day in advance and notify the exact blasting time 6 hours ahead.
(4) Provide the blasting network diagram, blasting parameters and blast source coordinates, and state the minimum safety distance.
(5) Help clear obstacles at monitoring points, level the sensor embedding spots and measure monitoring point coordinates.
(6) Coordinate on-site monitoring and safety guarding, and specify the guarded area.