1. Three-dimensional impact recorder for transformer transportation
Due to their excessive mass, large transformers cannot be transported with oil inside; therefore they are filled with nitrogen so that the core and windings do not contact air, avoiding moisture absorption by the insulation. A nitrogen-filled transformer must always keep the nitrogen pressure positive to prevent seal failure. After the nitrogen is released, qualified transformer oil shall be filled in immediately. When releasing nitrogen, attention shall be paid to personal safety. During transportation, the transformer shall be equipped, according to the specifications, with a three-dimensional impact recorder with time marking and an appropriate measuring range. Upon arrival at the destination, personnel of the manufacturer, the transport department and the user shall jointly carry out acceptance; the recording paper and the escort records shall be provided to the user for retention. Under normal circumstances, the manufacturer shall ensure that the structural (design) strength of the transformer can withstand at least 3 g of impact acceleration, ensuring that the transformer is not damaged when transportation impact is < 3 g; the transport devices and safety measures adopted by the transport enterprise shall be accepted and considered on the basis of withstanding at least 0. 25 g of impact acceleration, and at the same time the impact acceleration shall be controlled at ≤0. 25 g during transportation to ensure transportation safety.
2. Monitoring nitrogen leakage of nitrogen-filled transformers in transit
Usually a pressure gauge capable of measuring -98 to +98 kPa is used to monitor the internal pressure. After the transformer arrives, the pressure changes shall be monitored frequently before replacing the nitrogen with oil. Whether the nitrogen leaks can be judged according to Boyle's law.
Boyle's law: P / (273 + t) = P' / (273 + t')
Where : P is the pressure when nitrogen is filled, kPa; t is the temperature when nitrogen is filled, ℃; P' is the pressure at measurement, kPa; t' is the temperature at measurement, ℃; the values of P and t are provided by the manufacturer.
3. The following matters shall be noted when transporting and hoisting power transformers:
(1) The inclination of the power transformer shall not exceed 15%.
(2) Vibration and collision of the transformer shall be prevented. During transportation, the transformer shall be equipped with a three-dimensional impact recorder; if there is an impact exceeding 3 g, internal inspection must be carried out. The three-dimensional impact recorder shall be removed only after the transformer is installed in position, and the recorded data shall be submitted to the user as the basis for safe transportation and hoisting of the transformer.
(3) The transformer bushings, oil conservator, thermometer, gas relay, radiating pipes, explosion-proof duct, etc. cannot withstand large mechanical forces; these parts and devices must not be collided with during transportation and hoisting.
(4) When hoisting the transformer, the specially provided lifting rings under the oil tank shall be used to bear the load; the radiating pipes cannot bear weight, otherwise damage, oil leakage, bending or deformation will occur.
(5) The power transformer shall be kept balanced during transportation, strictly preventing core displacement and overturning that would cause internal mechanical damage. Transformers with voltage classes of 110-220 kV are transported filled with nitrogen.
4. Working procedures and technical requirements of on-site oil replacement
(1) Receiving the insulating oil: check whether the quantity of insulating oil equals the required amount. Store the insulating oil in dedicated oil tanks. Take oil samples for tgδ, insulation resistance and oil withstand voltage tests. The standards are: the oil breakdown voltage shall not be less than 40 kV / 2.5 mm, and tgδ shall be less than 0.5% at 90℃. The volume resistivity of new oil shall be greater than 1x10^14 Ω·cm (at 50℃). The water content in the oil may not be measured.
(2) Oil replacement: release nitrogen while injecting qualified insulating oil (the breakdown voltage of the oil shall not be less than 40 kV / 2.5 mm) until the core and windings are fully immersed in oil. After standing for more than 12 h, the oil may be drained for work inside the tank. For nitrogen-filled transformers and reactors that have not been fully purged of nitrogen (with gas oxygen density > 18%), it is strictly forbidden for workers to enter. When oil is injected into a nitrogen-filled transformer, no one shall stay near the vent hole.
5. Tests of the gas relay before installation and use
(1) Seal test: apply oil pressure to the whole body (pressure of 200 kPa; duration of 1 h) for leakage test, and there shall be no leakage.
(2) Terminal insulation strength test: the outgoing terminals and between the outgoing terminals shall withstand a power frequency voltage of 2000 V for 1 min; alternatively, the insulation resistance can be measured with a 2500 V megohmmeter, shaking for 1 min instead of the power frequency withstand test, and the insulation resistance shall be above 300 MΩ.
(3) Light gas operation volume test: when 250-300 cm3 of air accumulates in the casing, the light gas relay shall operate reliably.
(4) Heavy gas operation flow rate test: for naturally oil-cooled transformers the operating flow rate shall be 0.8-1.0 m/s; for forced oil circulation transformers it shall be 1.0-1.2 m/s; for transformers with capacity greater than 200 MVA it shall be 1.2-1.3 m/s.
6. Transformer test items
Insulation tests: insulation resistance and absorption ratio tests, dielectric loss tangent measurement, leakage current test, transformer oil test, power frequency withstand and induced withstand voltage tests; for transformers with Um not less than 220 kV, partial discharge tests shall also be carried out. For transformers with Um not less than 300 kV, full wave and switching impulse tests shall be done on the line terminals. Characteristic tests: transformation ratio, vector group, DC resistance, no-load, short-circuit, temperature rise and sudden short-circuit tests.
7. Phased tests of transformers
(1) Factory tests. Factory tests are relatively comprehensive tests, mainly to determine the electrical performance and technical parameters of the transformer, such as insulation, dielectric insulation, dielectric loss angle, leakage current, DC resistance, oil withstand voltage, power frequency and induced withstand voltage tests. If Um is not less than 300 kV, full wave and switching impulse tests shall be done on the line terminals. Technical parameter tests such as no-load loss, short-circuit loss and transformation ratio vector group determine whether the transformer can leave the factory.
(2) Preventive tests. That is, periodic scheduled tests on transformers in operation. The main test items are: insulation resistance, tgδ, DC resistance and oil tests.
(3) Overhaul tests. The test items are determined according to specific circumstances.
(4) Installation tests. That is, tests before and after the installation of the transformer. Test items include insulation resistance, dielectric loss angle, leakage current, transformation ratio, vector group, oil withstand voltage and DC resistance, etc. For large and medium-sized transformers, core lifting inspection must also be carried out. During core lifting, the clamping bolts, clamps and core must be tested. Finally, the power frequency withstand test is carried out. For transformers with voltage class of 220 kV and above and capacity of 120 MVA and above, on-site partial discharge tests must be carried out upon new installation.
8. Others
Obtain from the manufacturer the factory inspection reports of main materials and accessories and the factory test reports; during factory tests, the supplied bushings shall be installed on the transformer for testing; all accessories shall have been pre-assembled as a whole in the actual manner of use when leaving the factory.