| Inspection Contents and Standards for Blasting Project Construction Sites | ||
| Inspection Item | Inspection Standard | Remarks |
| Construction Notice | The notice shall state 6 items: the name and grade of the blasting project, the entrusting unit, the blasting design and construction unit, the project leader and project technical director, the blasting safety assessment unit and its assessment leader, the blasting safety supervision unit and its project leader, and the blasting operation time limit | 3 days before blasting construction (Hung or placed at the site during construction) |
| Blasting Notice | The notice shall state 5 items: the blasting location, each blasting time, the safety warning range, warning signs, and the initiation signal | 1 day before blasting construction (Pay attention to the distribution scope to avoid causing public panic) |
| Wearing Badges | The front of the badge states the unit, name, position, certificate grade and certificate number; the back states the position responsibilities | The relevant contents shall be clearly legible |
| Staffing | Each blasting project construction site shall be staffed with at least 1 blasting engineering technician corresponding to the project grade and scope, at least 1 safety officer, and at least 2 blasters (for tunnel, underground and open-pit shallow-hole blasting, after a single-shot explosive quantity of ≥100 kg, 1 additional blaster for each additional 100 kg. For open-pit deep-hole blasting with 1500 kg > single-shot explosive quantity ≥500 kg, at least 3 blasters; for single-shot explosive quantity ≥1500 kg, at least 4 blasters; after the single-shot explosive quantity exceeds 1500 kg, 1 additional blaster for each additional 2000 kg) | Only the minimum staffing is specified For the number of blasting personnel, in actual work the number can only be more, not less |
| Auxiliary Personnel | After safety training, under the supervision of the safety officer, they may carry boxes of explosives | Auxiliary personnel shall not carry opened boxes of explosives or detonators |
| Supervision Personnel | The chief safety supervisor of the blasting project holds safety operation certificates corresponding to the project grade and scope; Class A blasting projects shall have at least 1 senior blasting engineering technician, and Class B and below blasting projects shall have at least 1 intermediate blasting engineering technician | The supervision company may send blasters as auxiliary technical personnel to carry out supervision work |
| Construction Conditions | Where the construction environment conditions or geological conditions change significantly, the blasting design and construction unit shall notify the head of the safety assessment unit to inspect the site and determine whether the blasting design scheme and safety measures need to be readjusted and re-evaluated | When the construction environment and conditions change, the safety assessment unit needs to confirm whether a re-assessment is required |
| Temporary Storage | When 2 or more blasting operations are needed on the same day, a movable explosive storage magazine shall be used as the temporary storage place, and the temporary storage quantity shall not exceed the daily usage | Unused explosives shall be promptly returned to the warehouse or destroyed at the blasting site, with records kept (signed by the blaster, safety officer, supervisor and project technical director) |
| Site Requirements | 2 people patrol and guard; the blaster and storekeeper lock the magazine separately; wire mesh fencing is set with a height ≥2 m; video surveillance equipment is installed with image retention ≥30 days; the quantity of explosives does not exceed the magazine rated capacity and the daily usage; fire-fighting equipment is available; open flames are strictly prohibited within 50 m around; the duty room has an alarm telephone | Explosives and detonators are stored in separate magazines |
| On-Site Transportation | When transporting explosives from the temporary storage place to the blasting working face, other operations shall be stopped and unrelated personnel cleared; explosives and detonators are transported in separate vehicles, and no other personnel may ride in the vehicles | It is prohibited to use dump trucks, dump tipper trucks, bicycles, motorcycles or animal-drawn vehicles to transport explosives |
| Construction Records | Truthfully record the blasting construction process, blasting results, abnormal blasting situations and accidents, and regularly check against the supervision records; correct any errors immediately upon discovery | Carefully fill in the explosives and detonators usage record forms, kept for more than two years for reference (the records shall comprehensively document the whole process from the explosives arriving at the construction site to final use) |
| Inspection and Acceptance | The project technical director of the blasting project shall coordinate well with the owner unit and reasonably set up the safety warning zone; after blasting ends and safety is confirmed with records kept, other personnel may enter the blasting site | Inspection and acceptance written records shall be left for future inspection |
| Note: At the temporary storage point of the blasting site, not only must the storekeeper record the receipt, distribution, return and final disposal of unused explosives, including types, quantities and times, but each blaster must also record in detail the specific use time of the received explosives, so as to cross-check with the storekeeper's registration. | ||