Our company provides blasting vibrometers, suitable for monitoring various man-made seismic wave vibrations caused byblasting vibration. For details, consult 028-85238246
(1) Blasting parameter design control: through blasting tests, optimize the blasting design and strictly control the charge quantity. For vertical sidewalls excavated by benches, presplit blasting is adopted; for contour lines excavated horizontally, smooth blasting is adopted; for geological weak planes and important parts (such as the rock anchor beams of the powerhouse), excavation with reserved protective layers is adopted; for curved sections and arc sections, dense holes, shallow holes and short-cycle excavation are used to reduce final hole deviation.
(2) Safety protection measures: when excavating underground caverns by blasting, because the cavern space is narrow while the flyrock safety distance is large, when necessary, laying wire mesh, covering with sandbags or setting up bamboo fence protective walls are adopted to ensure blasting safety.
(3) Construction survey control: construction surveying is carried out by professional personnel, using infrared electro-optical rangefinders with levels. During construction, before each blasting drilling cycle, surveying and setting-out shall be carried out according to the construction drawings, and the overbreak-underbreak of the previous cycle shall be checked.
(4) Drilling quality control: drilling machinery must be operated by skilled workers with operating qualifications and work certificates; drilling is carried out by zones, sections, fixed personnel and fixed positions. Hole positions are determined according to the design and based on survey data; blasthole positions, directions and depths must all meet the design requirements, achieving accuracy, straightness, levelness, verticality and neatness.
(5) Charging quality control: before charging, blow the holes clean with high-pressure air to avoid affecting charging quality due to rock powder blockage. When charging, determine the charge quantity, charge density and charge structure per hole according to the design and actual conditions; hole mouth stemming shall be of sufficient length and firmly packed.
(6) Initiation circuit connection quality control: in-hole millisecond delay blasting circuits are adopted. Pay attention to controlling the single-shot charge quantity, blasthole initiation sequence and the interval between front and rear rows. Connect according to the designed circuit, and check for missed stemming of blastholes, missed connection of shock tubes, and whether the shock tube propagation direction has knots or kinks.
(7) At tunnel fork bifurcations, the small bench method is adopted for excavation, with shallow-hole short-cycle operations, single-cycle advance not greater than 1.5 m, minimizing over-excavation to ensure the effective dimensions of the contour line.
Our company provides blasting vibrometers, suitable for monitoring various man-made seismic wave vibrations caused byblasting vibrationmonitoring of man-made seismic wave vibrations caused by blasting. 028-85238246