Layout Point Selection of Blasting Vibration Meters in Blasting Vibration Monitoring

Zhongke Instruments · News2016-01-09 17:03:08

Home/News/Layout Point Selection of Blasting Vibration Meters in Blasting Vibration Monitoring
Content

Layout Point One: Ordinary Ground Buildings

1. The building vibration control point is on the building foundation or at the bottom of the main load-bearing exterior walls of the foundation slab;

2. For buildings higher than four stories (12 meters), measuring points shall be set every four stories and at the top story;

3. For structures longer than 10 meters, a measuring point shall be set approximately every 10 meters along the horizontal direction;

4. For vibration monitoring of precision instruments and other devices, measuring points shall be set on the foundation or the structural members of the equipment;

 

Layout Point Two: Tunnels and Roadways

1. The blasting vibration control point for tunnels and roadways is at a distance of 10-15 m from the blast source;

2. When excavating underground powerhouses by blasting, measuring points are arranged on the sidewalls; the nearest measuring points should be arranged within 10 meters of the edge of the blasting zone;

3. When blasting in adjacent caverns with an inter-cavern distance less than 1.5 times the average cavern diameter, monitoring points shall be arranged in both the adjacent cavern and this cavern;

 

Layout Point Three: High Rock Slopes

1. The blasting vibration control point for high slopes is at the inner slope toe of the upper berm;

2. The number of measuring points shall be no fewer than 3; the nearest measuring points should be arranged within 10 m of the edge of the blasting zone;

3. Where there are underground caverns in the slope body, corresponding measuring points are arranged on the cavern wall nearest to the blasting zone at about 1/3 of the cavern height from the floor;

4. Particle measuring points arranged in the rock mass are 3-5 m from the surface;

 

Layout Point Four: Parallel and Crossing Lines

1. Where the new tunnel is parallel to or crosses the existing tunnel, 2-3 key monitoring cross-sections are set at the crossing points and in the direction of the blast-facing surface;

2. Monitoring points should be set on the sidewalls of both sides, the tunnel floor and the crown of each monitoring cross-section;

3. When the new tunnel is above the existing tunnel, monitoring points shall be set on the crown; when below, it depends on installation difficulty and the minimum proximity;

4. Adjust the monitoring cross-sections and measuring points at any time according to construction progress;

 

For specific questions on selecting the layout method of blasting vibrometers in blasting vibration monitoring, please contact our customer service staff!