中文

News

Management Requirements for Blasting Projects

Zhongke Instruments · News2015-01-09 17:12:08

Home/News/Management Requirements for Blasting Projects
Content

Blasting vibrometer - Management requirements for blasting projects - Blasting vibrometer price - Zhongke Measurement and Control blasting vibrometer series products

GAICS 71.100.30G 89

 

Public Security Industry Standard of the People's Republic of China 

GA  991—2012

  

Management Requirements for Blasting Projects 

 

Blasting vibrometer - Management requirements for blasting projects - Blasting vibrometer price - Zhongke Measurement and Control blasting vibrometer series products

 

Foreword 

 

All the contents of this standard are mandatory.

This standard is drafted in accordance with the rules given in GB/T 1.1-2009.

This standard was proposed by the Public Security Administration Bureau of the Ministry of Public Security.

This standard is under the jurisdiction of the Technical Committee on Standardization of Fundamental Application for Social Public Security of the Ministry of Public Security.

The main drafting organization of this standard: the Public Security Administration Bureau of the Ministry of Public Security.

The main drafters of this standard: Yan Zhengbin, Qi Xiguo and Zhang Guoliang.

This standard is issued for the first time. 

 

The Regulations on the Safety Administration of Civil Explosive Materials (State Council Decree No. 466) stipulate that for blasting operations implemented near cities, scenic spots and important engineering facilities, the blasting operation unit shall apply to the public security organ of the municipal people's government (of a city divided into districts) at the location of the blasting operations, and submit the Blasting Operation Unit License and the blasting design and construction plan assessment report issued by a safety assessment enterprise with corresponding qualifications. When implementing blasting operations, supervision shall be carried out by a safety supervision enterprise with corresponding qualifications.

Authorized by the Regulations on the Safety Administration of Civil Explosive Materials, and on the basis of thorough investigation and extensive solicitation of opinions from relevant departments and industry units, this standard stipulates that blasting operations implemented near cities, scenic spots and important engineering facilities may only be implemented after approval by the municipal public security organ (of a city divided into districts) at the location of the blasting operations, and specifies the main contents of safety assessment, safety supervision, construction notice and blasting notice. This standard also makes specific requirements for the daily management of blasting projects, the purchase, storage and stocking of civil explosive materials, and the mixed charging truck operation system.

Management Requirements for Blasting Projects

1  Scope

 

This standard specifies the classification of blasting projects and the management requirements for blasting projects.

This standard applies to the management of blasting projects.

 

2  Normative References

 

The following documents are indispensable for the application of this document. For dated references, only the dated version applies to this document. For undated references, the latest version (including all amendments) applies to this document.

GB 6722  Safety Regulations for Blasting

GB 50089  Safety Code for Design of Civil Blasting Materials Engineering

GA 990  Qualification Conditions and Management Requirements for Blasting Operation Units

 

3  Terms and Definitions

 

The terms and definitions defined in GB 6722 and GA 990 apply to this document.

 

4  Classification of Blasting Projects

 

The classification of blasting projects is carried out according to GB 6722.

 

5  Management Requirements

 

5.1  Blasting Project Licensing

 

5.1.1  Safety Assessment

 

5.1.1.1  For blasting projects requiring approval by public security organs, before submitting the application, safety assessment shall be carried out by a blasting operation unit that meets the requirements of GA 990 and has corresponding qualifications.

5.1.1.2  The safety assessment shall include the following main contents:

a) Whether the qualification of the blasting operation unit meets the regulations;

b) Whether the grade of the blasting project meets the regulations;

c) Whether the data on which the design is based is complete;

d) Whether the design methods and design parameters are reasonable;

e) Whether the initiation circuit is reliable;

f) Whether the selected design scheme is feasible;

g) Whether the existing harmful effects and their possible scope of influence are comprehensively considered;

h) Whether the measures to ensure the safety of the project environment are feasible;

i) Whether the formulated emergency plans are appropriate.

 

5.1.2  Application

 

For blasting operations implemented near cities, scenic spots and important engineering facilities, the blasting operation unit shall apply to the municipal public security organ (of a city divided into districts) at the location of the blasting operations, and submit the Blasting Project Licensing Approval Form (see Annex A) and the following materials:

a) The Blasting Operation Unit Licenses and business licenses held by the design and construction, safety assessment and safety supervision units, and their copies;

b) The blasting operation contract signed between the design and construction unit and the entrusting unit;

c) The safety assessment contract signed between the safety assessment unit and the entrusting unit;

d) The safety supervision contract signed between the safety supervision unit and the entrusting unit;

e) The safety assessment report of the blasting design and construction plan issued by the safety assessment unit.

5.1.3  Approval

The public security organ accepting the application shall complete the review within 20 days from the date of acceptance. For those meeting the conditions, a decision of approval shall be made; for those not meeting the conditions, the reasons shall be explained to the applicant in writing.

5.1.4  Safety Supervision

5.1.4.1  For blasting projects approved by public security organs, when implementing blasting operations, safety supervision shall be carried out by a blasting operation unit that meets the requirements of GA 990 and has corresponding qualifications.

5.1.4.2  The safety supervision shall include the following main contents:

a) Whether the blasting operation unit constructs according to the design scheme;

b) Whether the harmful blasting effects are controlled within the design range;

c) Verifying the qualifications of blasting personnel and stopping unqualified personnel from engaging in blasting operations;

d) Supervising the implementation of the receipt and return system for civil explosive materials;

e) Supervising the implementation of compliance by the blasting operation unit with relevant national standards and codes; upon discovering illegal commands and illegal operations, having the right to stop its blasting operations and report to the entrusting unit and the public security organ.

5.2  Other Management Requirements

5.2.1  Construction Notice 

5.2.1.1  The blasting operation unit shall issue the construction notice 3 days before construction.

5.2.1.2  The construction notice shall include the following main contents:

a) Name of the blasting project;

b) Entrusting unit;

c) Design and construction unit;

d) Safety assessment unit;

e) Safety supervision unit;

f) Blasting operation time limit.

5.2.2  Blasting Notice

5.2.2.1  The blasting operation unit shall issue the blasting notice 1 day before blasting.

5.2.2.2  The blasting notice shall include the following main contents:

a) Blasting location;

b) Each blasting time;