Home › Case Studies › Construction Vibration Monitoring of a Xiamen Metro Ventilation Shaft

Construction Vibration Monitoring of a Xiamen Metro Ventilation Shaft

Monitoring Scene

Success case

Instrument

TC-4850

Category

Case Studies

Construction Vibration Monitoring of a X 4
  • Construction Vibration Monitoring of a X 5

Construction vibration monitoring of a Xiamen metro ventilation inclined shaft

Project overview: the mined section between Wengjiao Road and Maqing stations undercrosses Caijianwei Mountain at depths of about 17-238 m (max 238 m); the 2,702 m right and 2,696 m left running tunnels use the mining method. A ventilation inclined shaft on the right provides construction and operation ventilation. As excavation vibration affects the surroundings, TC-4850 blasting vibration meters were used for monitoring, providing reference for blasting safety and charge design.

Project overview: the mined section between Wengjiao Road Station and Maqing Station undercrosses Caijianwei Mountain at depths of about 17-238 m (max 238 m). The 2702 m right and 2696 m left running tunnels use mining method. A ventilation inclined shaft on the right provides construction and operation ventilation.

As excavation vibration affects the surroundings, TC-4850 blasting vibration meters were used for monitoring, providing reference for blasting safety and charge weight.

Construction Vibration Monitoring of a Xiamen Metro Ventilation Shaft