中文

Home/ProductsIn-house R&D and manufacturing

Products

Blasting vibration meters, sensors, bridge and transport monitoring, micro-seismic location and high-speed acquisition.

Home › Case Studies › Remote Vibration Monitoring in the Great Wall Sensitive Zone

Remote Vibration Monitoring in the Great Wall Sensitive Zone

Monitoring Scene

Success case

Instrument

TC-4850N

Category

Case Studies

Remote Vibration Monitoring in the Great 4
  • Remote Vibration Monitoring in the Great 5

Remote vibration monitoring in the sensitive zone of the Great Wall

In May 2017, a third-party testing agency purchased 5 TC-4850N wireless network vibration meters from us to monitor the sensitive core zone of the Great Wall during construction of Badaling Great Wall station. Construction of the Badaling tunnel on the Beijing-Zhangjiakou HSR has started. As the world's deepest underground HSR station, the 12.01 km Badaling tunnel crosses the core area of the Badaling Great Wall with many national-treasure relics, and national scenic spots such as Juyongguan and Shuiguan Great Wall along the line. Undercrossing the Great Wall is no easy task: the tunnel crosses two geological fault zones with rockburst, collapsible loess and large deformation of soft rock

In May 2017, a third-party testing agency purchased 5 TC-4850N wireless network vibration meters from us, mainly to monitor the sensitive core zone of the Great Wall during construction of Badaling Great Wall station.

Construction of the Badaling tunnel on the Beijing-Zhangjiakou HSR has started. As the world's deepest underground HSR station, the 12.01 km tunnel crosses the core area of the Badaling Great Wall, rich in national-treasure relics, with national scenic spots such as Juyongguan and Shuiguan Great Wall along the line.

Undercrossing the Great Wall is no easy task: the Badaling tunnel crosses two fault zones with high-risk geology including rockburst, collapsible loess and large soft-rock deformation - all extremely high construction risk; any carelessness could cause collapse. Meanwhile, environmental and heritage protection requirements are very strict, demanding zero surface settlement. How to achieve "HSR tunnel in harmony with the environment"?

The Badaling tunnel adopts "precise micro-blasting": traditional blasting produces vibration of 5 cm/s - quite strong, rattling car windows - while the new technology keeps it at only 0.2 cm/s, like a passing car, causing no damage to relics.

Multiple sensitive points of the Great Wall are tested with TC-4850N wireless network vibration meters, remotely monitoring site vibration in real time to protect the national-treasure Great Wall.