Safe Operation Procedures for Blasting Operations

I. General Provisions for Drilling and Blasting Operations

    1. Blasting operations shall strictly implement the provisions of the Blasting Safety Regulations and the Civil Explosive Articles Safety Management Regulations.

    2. Before blasting starts, complete the blasting construction approval procedures with the local public security organ with relevant documents; only with the blasting permit from the public security organ may explosive articles be collected and work started.

    3. Blasting personnel must undergo special technical and safety training, pass the public security examination, and hold a Blasting Safety Operation Certificate before taking up work.

    4. Before work, wear a safety helmet, work clothes and work shoes; wearing spiked shoes or static-prone synthetic clothing and drinking before shifts are strictly prohibited.

    5. For deep-hole blasting, chamber blasting, demolition blasting and controlled blasting, the blasting engineer shall prepare the Blasting Design Scheme, Blasting Design Specification and Blasting Construction Organization Plan according to the grade and scope specified in the Safety Operation Certificate; after review by the company chief engineer and approval or safety assessment by relevant departments, blasting construction may proceed.

    6. For mine or engineering geotechnical deep-hole blasting, before drilling and blasting operations, each blasting zone shall issue the Blasting Operation Specification according to the blasting safety technology determined in the Blasting Design Scheme, completing work division and technical guidance arrangements.

    7. Blasting operations must strictly follow the requirements of the Blasting Operation Specification, obey the directions of the on-site blasting supervisor and blasting technicians, and accept the supervision of safety officers.

    8. If blasting operations encounter situations inconsistent with the Blasting Operation Specification, or seriously threatening operational safety, report to the blasting technicians and relevant leaders; work shall resume only after the technicians revise the blasting scheme.

9. During charging operations, carrying matches, lighters and other ignition items is strictly prohibited, as is smoking in the workplace.

    10. Blasting operations are strictly prohibited under any of the following circumstances:

10.1 Expired or deteriorated explosives - blasting strictly prohibited;

10.2 Detonators without codes or past their validity - blasting strictly prohibited;

10.3 Explosive materials of unknown properties - blasting strictly prohibited;

10.4 Loading non-water-resistant explosives in wet holes - blasting strictly prohibited;

10.5 Charging blastholes with special geological structures or large terrain variations without control measures - blasting strictly prohibited;

10.6 Complex safety environments without controlled blasting technology - blasting strictly prohibited;

10.7 Two adjacent mines initiating without prior communication - blasting strictly prohibited;

10.8 Danger of collapse or landslide, etc.

10.9 Heavy fog, winds above force 6, rainstorms or thunderstorms - blasting strictly prohibited.

10.10 Mines with expired mining permits, boundary-crossing mining, or ordered to suspend production for rectification by superior authorities - blasting prohibited.

    II. Safe Operation Procedures for Blasting Operations

(1) Drilling and Hole Verification

1. Drilling

(1) Before drilling, the ground surface and cliff edge lines of the blasting area must be cleared, the safety environment of the blast zone inspected, the blasting method determined and the drilling design completed before hole layout.

(2) Hole layout shall avoid rock fracture zones and thick mud interlayers; the first row of blastholes shall keep a cliff-edge distance for safe rig operation of no less than 2.5 m.

(3) Position calibrated blastholes with woven bags and mark holes accurately with surveying instruments - estimation is not allowed. Label hole depth, dip angle and direction on plastic tags attached to the woven bags.

(4) During hole layout, the blasting technician and drilling supervisor shall operate together; after layout, the technician draws the hole layout diagram on site and gives the drilling technical briefing.

(5) Before drilling, clear gravel and soil near the hole position; determine the position per the designed depth and angle before starting. For deep holes, check the dip angle after drilling a certain depth, and continue until completion; cover the blasthole with rock powder in a woven bag.

  2. Hole Verification

 (1) After drilling, the blasting technician and rig supervisor check the completed holes against the layout diagram, cleaning and verifying holes one by one, recording hole depth, spacing, row spacing and dip angle. If the above parameters differ from the drilling design, discard or re-drill holes as appropriate, calculate the charge quantity and explosive type per hole, propose the explosive material approval and requisition plan, and the blasting engineer designs the Blasting Operation Specification.

 (2) Before charging, the blaster verifies hole depth and treats any blockage found.

(2) Blasting Operation Preparation

 1. The blaster prepares the tools and materials required for blasting:

  hole-measuring tape, tool bag, adhesive tape, hole-clearing rod or hammer, tamping pole, shovel, pick, initiation main line, initiation connection wires, warning flags, warning tape, walkie-talkies, alarms, initiation needle, blaster (initiating device), electric detonator tester, water buckets, filler plastic bags, filling funnels, detonator temporary storage box, tarpaulins, shock tube four-way connectors, various blasting records, etc.

 2. According to the initiation method and charging method, appropriately select the above tools and materials to carry for the blasting operation.

(3) Work Division and Technical Briefing

 1. Before blasting, the on-site supervisor assembles the blasters and safety officers in formation on site.

 2. The blasting technician gives the blasting safety technical briefing, and the on-site supervisor assigns work to each blaster.

 3. After the briefing, blasters sign the work division detail sheet and the Blasting Operation Specification.

(4) Requisition, Distribution and Storage of Blasting Materials

  1. Blasting materials use a delivery system: the blasting technical lead, safety officer and blaster receive materials on the transport truck arriving at the site, counting the types, quantities and specifications against the requisition plan with the escort, checking material quality, and distributing after confirmation.

  2. According to the technical briefing, blasters transport and distribute explosives to both sides of each hole per the charge quantity and explosive type of each hole, and collect the detonators needed for their assigned work.

  3. Remaining detonators must be placed in the detonator temporary storage box, which operates a two-person two-lock system - the safety officer and the blaster temporarily serving as custodian each hold a key. The explosive pile and the detonator box must be at least 25 m apart; the explosive pile and the detonator box must each be at least 25 m from the charging work point.

  4. Fill in the explosive articles requisition, use and return detail sheet; the escort, blasting technician, blaster and on-site supervisor each sign it.

  5. When transporting blasting materials, do not throw, smash or knock them - handle with care.

  6. Detonators received by blasters must not be placed on explosive boxes or bags; keep them properly in the tool bag. Littering is strictly prohibited; remaining materials are returned to the on-site custodian and must not be disposed of privately.

(5) Charging Guard

  Before charging, the blasting technician delineates the charging safety guard line; the safety officer plants warning flags at the line, clears unrelated personnel and movable machinery from the charging zone, and sets up isolation at the entrances to the blasting area, prohibiting entry of unrelated personnel and movable machinery.

  (6) Charging and Primer Preparation/Placement

 1. Before charging, the blaster checks for blockage with the tape measure, then charges with water-resistant or non-water-resistant explosives according to the water content of the hole.

 2. First charge the over-depth section of the hole; stop charging when in place, then prepare the primer.

 3. Primer placement:

 3.1 If a detonating cord initiation network is used, tie the primer cartridge to one end of the detonating cord and slowly lower it into the hole for positioning.

 3.2 If a shock-tube detonator initiation network is used, each hole shall use two millisecond detonators forming a duplex network: first assemble one in-hole detonator with the primer cartridge into a primer assembly and place it on the charge in the over-depth section; assemble the other in-hole detonator with a primer cartridge and place it at 1/3 of the upper charge section.

 3.3 If an electric initiation network is used, test each electric detonator for continuity and resistance error with the tester; reject detonators with resistance error greater than ±0.3 Ω. Note that the same initiation network must use electric detonators of the same manufacturer, batch and model. Tie the qualified detonators with the primer cartridge into a primer assembly and determine its position in the hole according to the legwire length and network connection form.

3.4 When using digital electronic detonators, pay attention to waterproofing of the wiring; check the detonator continuity before inserting into the hole.

  4. Charging procedure for each hole:pour charge → lower primer → pour charge → lower primer → pour charge.

 5. Charging safety notes:

 5.1 For wet holes, suspend one end of the cartridge with a rope hook and slowly lower it below the water surface; let cartridges settle by their own weight to contact each other - stones must not be allowed to fall in and separate the cartridges.

 5.2 When loading powdered explosives, do not pour too fast; prevent air-gap blockage in the hole. When powdered explosive cakes, cover half the hole with a board or stone while pouring; break up large lumps gently by hand or with a wooden stick before loading.

 5.3 When charging blockage occurs, a tamping pole may be used if the primer has not been loaded, or at least 0.5 m above the primer; if the primer itself or the explosive section containing it blocks the hole, using a pole to poke through is strictly prohibited.

(7) Stemming

 1. Before stemming, the blaster in charge measures the stemming height with the tape or pole to confirm it meets the safe stemming length specified in the technical briefing. Report any abnormality immediately to the blasting technical lead and on-site supervisor for supplementary charging, charge removal or hole-mouth protection.

  2. Use drilling rock powder as stemming material; stones (larger than 30 mm) and flammable materials are prohibited for stemming.

  3. Stem wet holes with rock cuttings - pour cuttings while draining, pull the initiation line to one side of the hole, and gently tamp the stemming section with the pole on the other side.

  4. For horizontal and gently inclined holes, after inserting each stemming cartridge or plastic roll with filler, push it gently into the hole with the tamping rod, then compact it.

  5. Stem with great care - do not damage the initiation circuit; tamping the stemming material in direct contact with the charge, or impacting the primer with stemming material, is prohibited.

  6. Pulling out or hard-drawing the detonating cord or shock tube leading out of the hole is prohibited.

(8) Initiation Network Wiring

1. After charging and stemming are complete and the site is cleared, sound the first warning signal; all unrelated personnel and explosive vehicles leave the blasting zone except the wiring personnel, cross-operations stop, the safety guard zone expands, and the initiation network is connected per the designed network layout diagram.

  2. When connecting the blasting network, prevent the plastic shock tubes from being stretched thin, broken, deformed or knotted; connect the detonating cord leading out of the hole to the main cord at an obtuse angle in the initiation direction.

  3. For surface millisecond delay initiation, no more than 20 initiation shock tubes may be tied to a relay detonator node; wrap the connection point with tape at least 3 layers, tightly and firmly.

4. For digital electronic detonator networks, be careful not to miss any connection. Check the network carefully; where surface water exists, prevent water ingress into the connectors. Operate per the manufacturer's training requirements to prevent misfires.

(9) Initiation Guard

  1. Per the guard scope determined in the blasting design and the on-site supervisor's instructions, the safety officer and guard personnel start from the charging guard line, clear unrelated personnel and movable equipment outward, block main traffic routes, take down the warning flags, reach their designated guard posts and hold them, plant warning flags at the guard line; guard points must have mutual line of sight and maintain radio communication with the initiation point.

  2. The blasting technician and wiring blaster re-check the laying quality and reliability of the initiation network, performing the "six checks": 1) whether the initiation sequence matches the design (to prevent excessive delay between later and earlier holes causing the crater of earlier holes to change the burden of later ones and produce flyrock); 2) whether any connections are missed; 3) the tying quality and tightness of connection points; 4) whether any shock tubes in the network are punctured, knotted or waterlogged; 5) whether in-hole and surface detonator delays and surface delay intervals contain errors; 6) whether the safety protection ensuring network transmission is in place.

  3. Confirm the initiation network connections are reliable, and cover surface connection points with rock-powder-filled woven bags or stones.

  4. Before initiation, check one by one the guard posts, evacuation of the guard zone, disposal of protected objects, the safe location of the initiation station and the initiation device test; then connect the initiation main line from the total network initiation end to the initiation station.

(10) Initiation

  1. After confirming the initiation network is correct, personnel at all guard posts report to the on-site supervisor the evacuation of personnel and machinery within the site and safety distance; only when initiation conditions are met may the supervisor issue the prepare-to-initiate command.

  2. The on-site supervisor contacts each guard post again via walkie-talkie to stay alert, sounds the initiation warning signal, and issues the countdown initiation command: "5, 4, 3, 2, 1" - initiate. Upon the warning signal, the initiator starts charging; upon the initiation command, the initiator presses the initiation button.

  3. After the blast, until the all-clear signal is issued, guard posts remain on alert; no person or vehicle may enter the blast zone except post-blast inspectors.

 (11) Post-Blast Safety Inspection

  1. After the blast, wait for the fumes to disperse; the on-site supervisor leads blasters, safety officers and technicians in a comprehensive, careful inspection of the blasting zone. Confirming no misfires, hangfires or hazards, sound the all-clear signal; guard posts remove warning flags and isolation tape and withdraw.

  2. If misfires or hangfires are found in the post-blast inspection, immediately notify the blasting technician or an experienced blaster to determine the cause and inform the unit leadership. If measures can solve it on site immediately, expand the guard zone before treatment; unrelated personnel must not approach the guard zone.

3. For misfires with major safety hazards that cannot be resolved immediately, set warning signs in the misfire zone, delineate the guard area and put up warning tape; no other work may enter the misfire zone. Immediately study the misfire treatment plan, report to unit leadership for approval, and assign experienced blasters, safety officers and technicians to the treatment. During treatment, guards must not withdraw.

  4. Per the Blasting Safety Regulations, when treating misfires and residual shots the following provisions must be observed:

 4.1 For electric initiation misfires, immediately cut the power and short-circuit the misfire in time. Test, straighten lines, find missed, wrong, short-circuited, broken or false connections, reconnect the network and initiate.

 4.2 For detonating cord and shock tube network misfires, check whether the network is damaged or broken; repair, check and re-initiate.

 4.3 For residual holes and missed-connection misfired holes, picking with picks, removing the original primer cartridge from the hole, or pulling the detonator out of the primer cartridge is strictly prohibited.

 4.4 After a misfired hole is treated and explodes, the blaster must carefully inspect the muck pile and collect unfired detonators and explosives.

 4.5 Before misfire treatment is complete, work unrelated to the treatment at that location is strictly prohibited.

 4.6 Misfire hole treatment must be performed under the guidance of the blasting technician or an experienced blaster, and completed within the shift; if not completed, the on-duty blaster must hand over clearly to the next shift's blaster on site.

 4.7 After treatment, the treater fills in the misfire treatment card, stating the cause, treatment method, result and preventive measures.

4.8 Misfires can also occur with digital electronic detonator initiation; treat per the misfire treatment specifications or the manufacturer's requirements.

(12) Return of Remaining Materials and Record Filling

 1. Count remaining materials and fill in the return form - "Explosive Articles Requisition, Use and Return Detail Sheet".

 2. Hand over returned materials to the escort on the delivery truck and load them per the detail sheet. After loading, the escort and the blaster temporarily in charge of storage sign the sheet; the escort returns the sheet to the civil explosives warehouse as the return form.

  3. Blasters carefully fill in the blasting records under the supervision of the safety officer.

  4. Destroy explosive packaging and residual shock tubes.

 (13) Post-Blast Summary

  1. The on-site supervisor assembles blasting personnel in formation on site; the blasting technician and drilling-blasting team leader summarize the implementation of the Blasting Operation Specification and the work division, the unsafe factors, hidden dangers and preventive measures in construction, technology, safety and blasting efficiency, propose measures to improve construction techniques, and summarize experience and lessons.

 2. The on-site supervisor asks the blasting personnel whether they have continuous improvement suggestions and what deficiencies existed in the organization of this blasting operation.

 3. The on-site supervisor announces the end of the blasting operation; blasters count their tools and materials, evacuate the site and return to camp.

 4. The entire blasting operation is video-recorded.